MTIB/SH(A)/001/2019
No. | Bidders Code | Price (RM) | Completion/Delivery Period |
---|---|---|---|
1. | 1/5 (Bumiputera) |
67,500.00 | 90 days |
2. | 2/5 (Bumiputera) |
73,142.00 | 90 days |
3. | 3/5 (Bumiputera) |
64,936.50 | 100 days |
4. | 4/5 | 74,895.00 | 21 days |
5. | 5/5 (Bumiputera) |
52,888.00 | 14 days |
6. | 6/6 (Bumiputera) |
57,070.00 | 3 weeks |
Note: The prices above are listed in the quotation documents received and prior to review by MTIB. MTIB is not bound to accept the lowest bid or vice versa.
Date : 4/03/2019